FABRIC COMMITTEE
Heating Pipes:
The new pipe work has
been functioning satisfactorily and the church is
heating up more quickly. It is hoped this will result in
some reduced gas heating bills. The treasurer will
compare usage with previous years and report
separately. It should certainly be a more reliable
system. Several new but identical metal gratings have
been sourced and fitted to replace those that were
broken or damaged.
Roof:
The architect has advised
that the north roof slope will require replacement
within the next 3 years. This major project will
require fundraising.
Churchyard:
Unfortunately several
conifer trees suffered damage during the heavy snowfalls
early in January. The PCC is liaising with a tree
surgeon to trim or possibly fell the affected trees if
good shapes cannot be restored. The grass and hedges in
the south cemetery will continue to be maintained by the
Havant community work team in 2010. Repairs will be
carried out on the external side of the churchyard wall.
Bell Tower:
The church architect
has drawn up a specification of the repair and
decoration works. Tenders have been received and (at the
time of writing) it is proposed to proceed with the
lowest tender of £3,029 plus VAT. The work should be
completed during May.
Lighting:
Following a preliminary
report by a lighting architect, the PCC has decided to
consider upgrading the lighting in the nave and chancel
as a first phase. An electrical report is being obtained
initially. The Winchester Diocese lighting adviser is
assisting.
Richard Marks (262599) |